Ryarsh Primary School
BackConstruction of a new school hall.
March 2019
Insulation laid ready for the floor screed.
December 2018
Insulation laid ready for the floor screed.
Installing the new windows.
Taking down the birdcage scaffold.
Installing the new air conditioning cassettes.
November 2018
We will remember them... The children decorated our site hoarding with poppies to commemorate the centenary of the armistice that ended World War I.
Preparing for the new roof
October 2018
Starting the brick and blockwork.
September 2018
Ongoing construction works.
Construction of block and beam floor and adjoining corridor.
Erection of new steel frame and start of brickwork.
August 2018
Site set up and groundworks for the new school hall.