Kent Farmhouse

Back

Construction of new nine bedroom house.

July 2020

Roof complete

Roof complete: details

June 2020

Felt and battening to the roof

Constructing the roof

Constructing the roof - details

Mansard roof steel frame complete.

Mansard roof steel frame.

Mansard roof block work and steels.

Carcassing the first floor.

Inserting the second floor steels.

May 2020

Feature cornicing.

Laying the first floor.

First floor joists and steelwork.

Feature stonework and decorative brick arches.

April 2020

Outfield drainage mound.

Starting the brickwork.

Inserting the steelwork on the ground floor.

March 2020

Formation of the soakaway.

March 2020

Work to the foundations.

Case Studies
Coxheath Primary School
Coxheath Primary School

Construction of a new single-storey extension. February 2018 Modular sections fu...

New Build Sevenoaks
New Build Sevenoaks

Construction of new house for private client. ...

Invicta House Car Park
Invicta House Car Park

Concrete repairs and resurfacing works. 3 September 2018 - Week 7 Surfacing comp...


Back to Top