Kent Farmhouse
BackConstruction of new nine bedroom house.
July 2020
Roof complete
960x720.jpg)
960x720.jpg)
Roof complete: details
720x720.jpg)
720x720.jpg)
720x720.jpg)
June 2020
Felt and battening to the roof
960x720.jpg)
960x720.jpg)
Constructing the roof
960x720.jpg)
960x720.jpg)
Constructing the roof - details
720x720.jpg)
720x720.jpg)
720x720.jpg)
Mansard roof steel frame complete.
960x720.jpg)
960x720.jpg)
Mansard roof steel frame.
960x720.jpg)
960x720.jpg)
960x720.jpg)
Mansard roof block work and steels.
960x720.jpg)
960x720.jpg)
960x720.jpg)
Carcassing the first floor.
960x720.jpg)
960x720.jpg)
Inserting the second floor steels.
720x720.jpg)
720x720.jpg)
720x720.jpg)
May 2020
Feature cornicing.
-960x720.jpg)
960x720.jpg)
Laying the first floor.


First floor joists and steelwork.


Feature stonework and decorative brick arches.



April 2020
Outfield drainage mound.



Starting the brickwork.


Inserting the steelwork on the ground floor.


March 2020
Formation of the soakaway.



March 2020
Work to the foundations.