Barham - New Build
BackThis project was featured in Episode 7 of the Sixth Series of Channel 4's Building the Dream with Charlie Luxton.
Watch how the house progresses and how we perform in the spotlight...
Spring 2017
Plot 'A' complete and landscaping established.
Interior finishes...
November 2016
Scaffold erected and shell construction started on Plot 'C'.
Scaffold down and shell complete on Plot 'A'.
August 2016
Blockwork for DPC and installation of drainage on Plot 'C'.
Roof and underfloor heating installation to Plot 'A'.
July 2016
Preparation of the footings for Plot 'C'.
June 2016
Installation of timber floor joists and flooring to Plot 'A' and start of construction on Plot 'B'.
Brickwork to Plot 'A'.
May 2016
Scaffolding in place ready for the erection of the timber frame.
April 2016
Ground level blockwork up to DPC with foul water and soil pipes in place. Steels then positioned to support the first floor flooring joists.
March 2016 - Plot 'A' is underway.
We are currently building three new, four bedroom houses in Barham.