Invicta House Car Park
BackConcrete repairs and resurfacing works.
3 September 2018 - Week 7
Surfacing complete line marking underway.
13 August 2018 - Week 5
Mastic repairs to joints.
Concrete patch repairs.
Parapet wall repairs and car park deck prepared for waterproof coatings.
Strengthening repairs to surface and upstands and base layers of waterproof coatings.
30 July 2018 - Week 3
Before and after the preparation of the car park decks for resurfacing.
23 July 2018 - Week 2
Continuation of break out of spalled and failing concrete and application of corrosion inhibitor and repair.
Removal of 4mm of car park surface in preparation for new resin covering.
Repairs to upstands and replacement of coping stones.
16 July 2018 - Week 1
Site set up, break out spalled and failing concrete and application of corrosion inhibitor.
Reinstatement of concrete
Removal of failed asphalt skirting and upstands and blastrac preparation of car park deck